Mersey Steel and Iron Co Ltd v Naylor, Benzon & Co
A buyer who withheld payment for one instalment on mistaken legal advice, while showing that it intended to perform the contract, did not repudiate the contract.
Facts
Mersey Steel agreed to sell steel to Naylor Benzon in monthly instalments, with payment due after each delivery. A winding up petition was presented against Mersey Steel, and Naylor Benzon, on legal advice, refused to pay for a delivery until the court had given leave, because it was concerned that it might not get a good discharge if it paid. Mersey Steel's liquidator treated this as a repudiation of the contract and refused to make further deliveries.
Legal principle
The House of Lords held that Naylor Benzon had not repudiated the contract, so Mersey Steel was liable for failing to deliver. Lord Selborne LC said that the question is whether the conduct of the party in breach amounts to a renunciation, an intimation of an intention to abandon and altogether to refuse performance of the contract. Naylor Benzon had made clear that it wished to continue the contract and was willing to pay, as soon as it could do so safely, so its refusal to pay the instalment was not a repudiation.
Related cases on discharge and breach
- Ampurius Nu Homes Holdings Ltd v Telford Homes (Creekside) Ltd [2013] EWCA Civ 577
- Avery v Bowden (1855) 5 E & B 714
- Bolton v Mahadeva [1972] 1 WLR 1009
- Cutter v Powell (1795) 6 Term Rep 320
- Decro-Wall International SA v Practitioners in Marketing Ltd [1971] 1 WLR 361
- Eminence Property Developments Ltd v Heaney [2010] EWCA Civ 1168
- Federal Commerce & Navigation Co Ltd v Molena Alpha Inc (The Nanfri) [1979] AC 757
- Fercometal SARL v Mediterranean Shipping Co SA (The Simona) [1989] AC 788
Studying contract law? Our tutors help you understand and apply cases like this in essays, problem questions and exams. Request a quote or browse our law notes.
This summary is for study and revision and is not legal advice. Although our case summaries are checked for accuracy, we do not guarantee that they are free from errors or omissions. Always read the full judgment for the court's reasoning.