British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd

A claimant must take reasonable steps to mitigate its loss, and benefits gained from those steps reduce its damages.

Citation
[1912] AC 673
Court
House of Lords
Year
1912
Subject
Contract Law
Topic
Remedies

Facts

British Westinghouse agreed to supply turbines to the Underground Electric Railways Company for a power station. The turbines did not meet the specification and were less efficient than promised, so they used more coal. After a few years, the railway company replaced them with new turbines from another manufacturer, which were much more efficient than even the turbines British Westinghouse had promised to supply. The savings in running costs from the new turbines exceeded the cost of buying them. The railway company claimed the cost of the replacement turbines as damages.

Legal principle

The House of Lords held that the railway company could not recover the cost of the new turbines, because the benefits it obtained from buying them more than outweighed their cost. Viscount Haldane LC said that the fundamental basis of damages is compensation for pecuniary loss naturally flowing from the breach, but this is qualified by the duty, imposed on the claimant, of taking all reasonable steps to mitigate the loss consequent on the breach. Where the claimant's steps in mitigation arise out of the transaction and reduce its loss, the benefit must be taken into account in assessing damages.

Related cases on remedies

Studying contract law? Our tutors help you understand and apply cases like this in essays, problem questions and exams. Request a quote or browse our law notes.

Back to all law cases

This summary is for study and revision and is not legal advice. Although our case summaries are checked for accuracy, we do not guarantee that they are free from errors or omissions. Always read the full judgment for the court's reasoning.

Contact Us

Enquire about our bespoke academic solutions