British Steel Corp v Cleveland Bridge and Engineering Co Ltd

Where work was done at a party's request in anticipation of a contract that was never concluded, the party doing the work was entitled to a reasonable sum, and there was no contract under which the recipient could claim damages.

Citation
[1984] 1 All ER 504
Court
High Court (Queen's Bench Division)
Year
1984
Subject
Restitution and Unjust Enrichment
Topic
Mistake, failure of basis, duress and services

Facts

Cleveland Bridge sent British Steel a letter of intent asking it to begin manufacturing steel nodes for a building project, pending the conclusion of a formal contract. The parties continued to negotiate but never agreed on important terms, such as price and liability for delay. British Steel made and delivered the nodes, and claimed a reasonable price. Cleveland Bridge counterclaimed damages for late delivery.

Legal principle

Robert Goff J held that no contract had come into existence, because the parties had never reached agreement on essential terms. British Steel was entitled to be paid a reasonable sum for the nodes on a quantum meruit, since they had been supplied at Cleveland Bridge's request and accepted by it. Since there was no contract, Cleveland Bridge could not claim damages for late delivery. The case illustrates the risks of proceeding with work on the basis of a letter of intent.

Related cases on mistake, failure of basis, duress and services

Studying restitution and unjust enrichment? Our tutors help you understand and apply cases like this in essays, problem questions and exams. Request a quote or browse our law notes.

Back to all law cases

This summary is for study and revision and is not legal advice. Although our case summaries are checked for accuracy, we do not guarantee that they are free from errors or omissions. Always read the full judgment for the court's reasoning.

Contact Us

Enquire about our bespoke academic solutions